Private landlords in England must have the electrical installation inspected and tested at least every 5 years, and give tenants the report within 28 days.
Who gets the report, and when
| Who | Deadline |
|---|---|
| Existing tenants | Within 28 days of the inspection |
| New tenants | Before they occupy the property |
| Prospective tenants | Within 28 days of a written request |
| The local council | Within 7 days of a written request |
Remedial work
If the report needs work doing, it must be done within 28 days, or sooner if the report says so.
Shorter intervals
If the electrician's report says the next inspection should be sooner than 5 years, that shorter interval applies.
FAQs
How often do landlords need an EICR?
At least every 5 years, or sooner if the report says.
How quickly must EICR remedial work be done?
Within 28 days of the inspection, or the shorter period the report specifies.
Do I give the EICR to the council?
Only if they ask in writing, within 7 days of the request.
Plan it in minutes
Enter the inspection date and interval, and the tracker shows when the next EICR is due and when remedial work must be finished.
See the Landlord Compliance Checklist →